These are provisional dates and are a guideline for me to sketch out a pathway to Lagos for the test run down to Lanzarote and then onto the starting line in Antigua for the MGR 2029. I realise that I should be puting down hours of work for this project but to be honest I am finding that difficult as I am standing, looking and wondering what to do a lot π
| Date | Event/Activity | Working Hours | Comments |
| 14/02/25 – 14/04/25 | Decide on and create a site to build the boat. | The build of base and erecting the tent took 1 week | There have been so many ideas on this. Anyway, it’s the back garden. Building a wooden platform 7.2m x 3.6m and covering with temporary work shelter. Just hope we can get it out when its finished!! ; |
| Ordered and will be collecting on 21/05/25 | Order CNC Kit. | The timeline needed to be adjusted due to supply of Okume. | |
| 22/05/25 – 01/11/25 | Phase 1: Learn,read and ask a lot of questions. Complete Frames. | 1.Seal Parts 2.Make Frames | |
| 01/11/25 – 01/02/26 | Winter Break | ||
| 15/02/26 – 01/11/26 | Phase 2: Complete hull to full planking glass fibre, fairing, paint and turn. | 1.Build Jig and Attach Frames 2.Attach Bunk Boards 3.Attach Cockpit Boards 4.Attach Stringers 5.Planking 6.Sanding and Planing 7.Tape Joints 8. Glassing Fairing, Paint,Skeg,Measure out plate fitting for Keel and Turn. | |
| 01/11/26 – 1/02/27 | Winter Break | ||
| 01/02/27 – 01/11/27 | Phase 3: Keel and Rudder Internals and upper part of boat. Electronics and navigation set up. Rigging and decking kit. | ||
| 01/11/27 -01/02/28 | Winter Break | ||
| 01/02/28 – 01/07/28 | Phase 4: Buy engine and windvane. Snagging and launch boat for sea trials.Check over boat and do any fixes then continue sea trials with windvane. | ||
| 01/07/28 -01/08/28 | Sail boat to Lagos. | ||
| 01/11/28 | Fly to Lagos for start of TRANSAT/ MGR checks. |